Project Status Report Template: How to Write One, With an Example

A project status report tells sponsors, a steering committee or a client whether one project is on track against its baseline. Unlike a weekly team report, which summarizes what people did, it compares scope, schedule, budget and quality with what was agreed at the start, and it makes clear which decisions are needed and by whom.

This page gives you a free Word and Excel template, a field-by-field guide, a filled budget-versus-actual example, criteria for red, amber and green, and the habits that stop a report from turning into a watermelon: green outside, red inside.

What is a project status report?

A project status report is a short, regular document that shows the overall health of a project at a point in time. It usually covers the overall RAG (red, amber, green) status, progress against milestones, budget spent versus planned, the top risks and issues, open change requests and the decisions the project needs. Most teams send it every two weeks or once a month, ahead of a steering committee or client meeting.

The point is not to prove that everyone is busy. It is to show where the project stands compared with its baseline and what it needs to finish. When dates and costs are always measured against the approved baseline, a sponsor can read the first page in a minute and know whether to act.

When do you need a project status report?

  • Reporting regularly to a sponsor, steering committee or project board
  • Giving a client contractual progress updates on an implementation or consulting project
  • Checking the project before and after a major milestone or stage gate
  • Asking for a decision on extra budget, a scope change or a new go-live date
  • Keeping several departments or vendors aligned on who is doing what

Project status report template: what to write in each field

The download has three parts. Write the first page so that a busy executive can decide from the status and the decisions box alone; put the detail in the tables.

Project details and overall status

FieldWhat to writeExample
Project name and codeThe official name and code used in the budget and contract.Customer portal relaunch (PRJ-118)
Project manager and sponsorWho runs the project and who owns the decisions.PM: Rachel Owens · Sponsor: VP Customer Success
Reporting periodReport number and dates covered.Report 6 · Oct 19–30, 2026
Overall status (RAG)Status for scope, schedule, budget and quality, plus one overall color and a one-line reason.Amber: data migration at risk of a two-week slip

Milestones

FieldWhat to writeExample
MilestoneThe deliverables and gates agreed at kickoff.User acceptance testing complete
Baseline dateThe approved plan date. Change it only through an approved change request.Nov 20, 2026
Forecast dateToday's best estimate.Dec 4, 2026
StatusDone, on track, at risk or late.At risk (migration data quality)

Budget, risks and decisions

FieldWhat to writeExample
Budget vs actualBudget, spend to date and remaining for each work package, plus percent spent.$190,500 of $320,000 spent (59.5%)
Risks and issuesProbability and impact, response, owner and due date.Legacy IDs don't match → mapping table signed off by Nov 6 (Dev lead)
Change requestsScope, schedule or budget changes and their approval status.CR-04 add SMS alerts: under review
Decisions neededWho must decide what, and by when, with the options.Move go-live from Dec 7 to Dec 14? Steering committee, Nov 10
Next periodThe three to five most important activities before the next report.Second migration rehearsal; confirm training dates

Project status report example

Report 6 for a customer portal relaunch. The overall status and the decision request sit at the top; the budget is broken down by work package.

ProjectCustomer portal relaunch (PRJ-118)
PeriodReport 6 · Oct 19–30, 2026
Overall statusAmber: data migration at risk of a two-week slip
Decision neededApprove moving go-live from Dec 7 to Dec 14 at the Nov 10 steering committee

Budget vs actual

Work packageBudgetActual to dateRemaining
Discovery and design$45,000.00$44,200.00$800.00
Build$180,000.00$131,500.00$48,500.00
Data migration$60,000.00$14,800.00$45,200.00
Training and rollout$35,000.00$0.00$35,000.00
Total$320,000.00$190,500.00$129,500.00

Milestones: design signed off (done); build complete Nov 13 (on track); UAT complete baseline Nov 20, forecast Dec 4 (at risk). Budget is green: 59.5% spent with build about 70% complete.

Free download

Free, no sign-up. Opens in Excel, Google Sheets, Numbers, Word, Google Docs and LibreOffice.

Open the downloaded file in Nobami, our web office, to edit it right away.

How to write a project status report

  1. Lock the baseline. Use the scope, dates and budget approved at kickoff, and change them only when a change request is approved.
  2. Update forecast dates, not baseline dates. Keeping the baseline visible next to the forecast is what makes a slip obvious.
  3. Pull actual spend by work package. Take spend to date from finance or purchase records and calculate remaining budget and percent spent.
  4. Set RAG with agreed criteria. For example: amber for a slip of up to one week, red for a slip on the critical path or a forecast overrun above 10%.
  5. Refresh the risk and issue log. Mark what is new and what is closed, and give every open item an owner and a date.
  6. Put decisions on page one and send it before the meeting. Give the options and the impact of each on time and cost, and send the report at least a day before the steering committee.

Good practice: governance and personal data

There is no legal format for a project status report, but public-sector and regulated organizations often set one. The UK government's functional standard for project delivery, for example, expects projects to have clear governance, a defined baseline and regular assurance reporting. Check your organization's or your client's governance rules before you design your own report.

Keep personal data out of the report. Stakeholder lists with phone numbers, real customer records used in testing and comments about individual performance are personal data under laws such as the GDPR. Use anonymized test data, refer to roles instead of names where you can, and store reports where access is controlled.

If the project changes a supplier's scope or price, record the change in a signed contract amendment, not only in the change request log of the status report.

Sources

General information, not legal advice. Contract terms, public-sector rules and privacy laws differ by country and organization; follow your internal policy and contract.

Common project status report mistakes

  • Watermelon reporting: the details show a delay but the overall status stays green
  • Rewriting baseline dates every period so that slips disappear
  • Showing only the total budget, with no breakdown or remaining amount
  • Listing risks without a response, an owner or a due date
  • Ending with 'for your review' when a specific decision is needed
  • Copying a team activity list into the report so that project health is buried

Project status report FAQ

How is a project status report different from a weekly status report?

A weekly status report covers what a person or team did this week and plans for next week. A project status report measures one project against its approved scope, schedule and budget so that sponsors can make decisions.

How do I decide red, amber or green?

Agree the criteria at kickoff. A common rule: amber when a milestone slips up to a week or the forecast overrun is under 5%, red when the critical path slips further or the overrun exceeds 10%. Every amber or red item needs a recovery action.

How often should I send it?

Every two weeks or monthly is typical. Increase to weekly before go-live or during high-risk phases, and send it a day before the steering committee meets.

Is it the same as meeting minutes?

No. The status report goes out before the meeting to set up the discussion and the decisions. The minutes record what was decided, and those decisions feed into the next status report.

Can I use the template in Google Docs or Sheets?

Yes. The Word file opens in Google Docs and the Excel file opens in Google Sheets, with the budget totals kept as SUM formulas.